We use strictly necessary cookies to make our site work. These cookies enable core functionality such as security, network management, and accessibility. The cookies collect information in a way that does not directly identify anyone. For more information on how these cookies work please see our privacy policy.

To agree to our use of analytical cookies, click the 'Accept cookies' button. No, give me more information.
Accept cookies Reject analytical cookies Manage cookies
 

CX031 Timeline for scheme of works

Road closures and diversions

(Dates as a guide only and are subject to change)

1

21.10.2024 – 23.10.2024 (07:30 - 3pm)

Coton Lane from the junction of the A513 Comberford Road and the southern junction of Fontenaye Road.
(Access to properties maintained via local diversion)
Further information: Utility Survey
2

24.10.2024 – 01.11.2024 (07.30 - 24hrs)

Coton Lane from the junction of the A513 Comberford Road to the north junction of Fontenaye Road.
(Access to properties maintained via local diversion)
Properties 1-25 Coton Lane Restricted driveway access
Further information: Carriageway reconstruction works and deep excavations. Restricted driveway access. Off road parking required
3

02.11.2024 – 06.11.24 (07.30 - 24hrs)

Coton Lane from the junction of the A513 Comberford Road to the north junction of Fontenaye Road.
(Access to properties maintained via local diversion)
Properties 27-37 Coton Lane Restricted driveway access
Further information: Carriageway reconstruction works and deep excavations. Restricted driveway access. Off road parking required
4

07.11.2024 – 15.11.2024 (07.30 - 24hrs)

Coton Lane from the junction of the A513 Comberford Road to the north junction of Fontenaye Road.
(Access to properties maintained via local diversion)
Properties 39-45 Coton Lane Restricted driveway access
Further information: Carriageway reconstruction works and deep excavations. Restricted driveway access. Off road parking required
5

15.11.2024 – 23.11.2024 (07.30 - 24hrs)

Fontenaye Road north to the junction of Fontenaye Road south. (Access to properties maintained via local diversion)
Further information: Carriageway reconstruction works and deep excavations
6

23.11.24 – 01.12.2024 (07.30 - 24hrs)

Fontenaye Road north to the junction of Fontenaye Road south. (Access to properties maintained via local diversion)
Properties The Elms, Briarwood and 49A Coton Lane Restricted driveway access
Further information: Carriageway reconstruction works and deep excavations
7

01.12.2024 – 04.12.2024 (07.30 - 24hrs)

Fontenaye Road north to the junction of Fontenaye Road south.
(Access to properties maintained via local diversion)
Further information: Carriageway reconstruction works and deep excavations
8

05.12.2024 – 08.12.2024 (07.30 - 5pm)

Coton Lane from the junction of the A513 Comberford Road and the southern junction of Fontenaye Road.
(Access to properties maintained via local diversion)
Further information: Carriageway resurfacing
9

09.12.2024 – 13.12.2024 (07.30 - 5pm)

Coton Lane from the junction of the A513 Comberford Road and the southern junction of Fontenaye Road.
(Access to properties maintained via local diversion)
Further information: Road markings

There are no results that match your search criteria