We use strictly necessary cookies to make our site work. These cookies enable core functionality such as security, network management, and accessibility. The cookies collect information in a way that does not directly identify anyone. For more information on how these cookies work please see our privacy policy.

To agree to our use of analytical cookies, click the 'Accept cookies' button. No, give me more information.
Accept cookies Reject analytical cookies Manage cookies
 

A34 Highway Improvements, Stafford. Town Centre to Weeping Cross

funded-by-uk-government

What are we doing?

We will be carrying out maintenance and infrastructure improvements along the A34 Corridor, from Weeping Cross to the Town Centre. 

The scheme includes road and transport improvements including road and bridge maintenance work, active travel, passenger transport and street lighting improvements on the A34, between Stafford Town Centre and the A34/A513 double traffic island junction at Weeping Cross.  

Roads affected include A34 Lichfield Road, North Walls, Queensville Roundabout, Queensville, Radford Bank, Baswich Lane, Cannock Road and Weeping Cross. 

The roadworks are planned to be carried out in eight phases. Works started in early June 2024 and are planned to be completed October 2025.  Bus services will be affected between Weeping Cross and Riverway. View further information.  

You can find frequently asked questions here. If you have any questions, please email luf.stafford@staffordshire.gov.uk 

Radford Bank road closure between Weeping Cross and Queensville Roundabout - 24 March to 25 April 2025

Radford Bank will be closed between 8pm – 6am for final surfacing works to all through traffic.

There will be access to all frontages and side roads between 2 April to 14 April 2025.

Access to frontages outside each phase will vary from each direction, dependant on work progress. Residents who live north of Radford Bank Bridge access off Queensville Roundabout and those south to access from Weeping Cross.

The surfacing will be carried out in phases where there will be no access / exit during the closure for residents / businesses within these extents.

During these dates if you need to get in / out of your property, we would ask that you park your vehicle on the adjacent roads outside of the working phase.

Please note: all dates and times are subject to changes should any delays occur due to poor weather or breakdowns

Phase 1 - between No. 20 Radford Bank and Entrance to Radford Bank Public House (including junctions of Lower Radford Rise and Meadow Ridge)

There will be no access to and from your property for one night:

  • Monday 14 April 2025

View phase 1 map (451 KB)

Phase 2 - between Entrance to Radford Bank Public House and No. 72 Queensville

There will be no access to and from your property for one night:

  • Tuesday 15 April 2025

View phase 2 map (442 KB)

Phase 3 - between No. 72 Queensville and Kent Way (Including junction to Windsor Road)

There will be no access to and from your property for three nights:

  • Tuesday 25 March 2025
  • Wednesday 26 March 2025
  • Thursday 17 April 2025

View phase 3 map (440 KB)

Phase 4 - between Kent Way and Queensville Roundabout (including junction to Kent Way)

There will be no access to and from your property for five nights:

  • Thursday 27 March 2025
  • Friday 28 March 2025
  • Monday 31 March 2025
  • Tuesday 22 April 2025
  • Wednesday 23 April 2025

View phase 4 map (449 KB)

Road closures on approaches to Queensville Roundabout (Silkmore Lane, A34 Queensville and Old Rickerscote Road (Queens Retail Park)

Silkmore Lane Road Closure - (between No. 33 Silkmore Lane, Queensville Roundabout and Entrance to Queens Retail Park)

There will be no access to and from your property for six nights:

  • Thursday 27/03/25
  • Friday 28/03/25
  • Thursday 24/04/25
  • Friday 25/04/25
  • Wednesday 30/04/25
  • Thursday 01/05/25

A34 Queensville Road Closure - (between No. 29 Queensville – Queensville Roundabout and Exit from Queens Retail Park, including The Glade)

There will be no access to and from your property for six nights:

  • Monday 31/03/25
  • Tuesday 01/04/25
  • Monday 28/04/25
  • Tuesday 29/04/25
  • Friday 02/05/25
  • Saturday 03/05/25

A34 Queensville Roundabout (central island)

The works are to be carried out in sections around the roundabout. A34 Queensville will be closed from 8pm – 6am, with temporary signals on approaches to allow access into Ampleforth Drive and Queens Retail Park (marshalled access). Access to The Glade and Queensville will be off A34 Lichfield Road. 

• Sunday 06/04/25

View Silkmore-Queensville map (494 KB)

We apologise for any inconvenience which may be caused, and we thank you for your continued patience throughout the duration of these essential works.

Phasing of the Works

This page will be updated as information changes and further detail will be added when this becomes available.

Phasing plan:

A34 Stafford improvements - phase plan (5 MB)

 

Phasing of the Works

This page will be updated as information changes and further detail will be added when this becomes available.

This is the phasing plan:

Key:

Phases that are currently in progress
Phases that will start shortly
Phases that have been completed

 

Phase 1 - Gaol Square (Completed September 2024)

Phase 2 - Weeping Cross Roundabout (Completed October 2024)

Phase 2a - Queensville Bridge - Below Deck (Completed October 2024)

Phase 3 - Radford Bank - Queensville Roundabout
Construction 01/09/24 - 23/04/25
Surfacing / Lining 17/03/25 - 23/04/25

  • Drainage Repairs and Improvements
  • Carriageway and Footway Resurfacing
  • Maintenance works to Radford River Bridge
  • Upgraded street lighting
  • New and Upgraded Pedestrian and Cycle Crossings
  • Shared Cycle/Footway Route
  • Further detail: Phase 3 - Radford Bank to Queensville Roundabout

Phase 4 - Queensville Roundabout
Construction 06/01/25 - 03/05/25
Surfacing / Lining 01/04/25 - 03/05/25

  • Drainage Repairs and Improvements
  • Carriageway and Footway Resurfacing
  • Upgraded street lighting
  • Upgraded pedestrian and cycle crossings

Further detail: Queensville Roundabout plan


Phase 5 - Queensville Bridge 
Construction 09/06/25 - 15/08/25 (for 10w)

  • Drainage Repairs and Improvements
  • Carriageway and Footway Resurfacing
  • Waterproofing and footway protection to Railway Bridge
  • Partial segregated cycle route
  • Shared cycle route over Railway Bridge

Further details will be released in due course


Phase 6 - Queensville Avenue - Riverway
Construction 09/06/25 - 15/08/25 (for 10w)

  • Drainage Repairs and Improvements
  • Carriageway and Footway Resurfacing (SCC Funded)
  • Improved Pedestrian Crossing Points
  • Existing Traffic Signal Upgrade

Further details will be released in due course


Phase 7a - Bridge Street - Lichfield Road (Gyratory)
Construction 18/08/25 - 26/09/25 (for 6w)

  • Pedestrian and Cycle Crossing/lane Improvement

Further details will be released in due course


Phase 7b - Bridge Street - Lichfield Road (Gyratory)
Construction 18/08/25 - 29/08/25 (for 2w)

  • Upgraded Pedestrian and Cycle Crossing
  • Bus Priority Measures between St. Leonard's Avenue & Bridge Street

Further details will be released in due course

Phase 8 - North Walls (Gaolgate Street - South Walls)
Construction 17/02/25 - 02/05/25 (for 11w)

  • Shared cycle route across Gaolgate Street
  • Advisory contraflow cycle lane North Walls (access road) to A34 Queensway
  • Further details on this phase: Phase 8 - North Walls

 