We use strictly necessary cookies to make our site work. These cookies enable core functionality such as security, network management, and accessibility. The cookies collect information in a way that does not directly identify anyone. For more information on how these cookies work please see our privacy policy.

To agree to our use of analytical cookies, click the 'Accept cookies' button. No, give me more information.
Accept cookies Reject analytical cookies Manage cookies
 

CX029 A449 Wolverhampton Road, Stafford

From A34/A449 Kwik Fit Roundabout to Ingestre Road/Railway bridge. 

Staffordshire County Council together with Amey will be carrying out drainage repairs, kerbing, footway patching and carriageway resurfacing at the above location.

 

When are the works taking place?

The Works will commence on 4 March 2024.

What is the duration of the works?

The  works are expected to take approximately 11 weeks.

Will I be able to access my home/business?

To minimise traffic disruption, the works will be carried out with temporary road closures as follows: 

  • One way road closure, all traffic permitted northbound towards Stafford Town only.

           From 4 March to 21 April.

           From 29 April to 12 May. 

  • Full road closures

           From 22 April for one week.

           From 13 May for one week. 

At various times, there will be a series of side road closures, signed diversions and one-way systems will be reversed to allow vehicular access.

Exact dates, times and access arrangements will be confirmed and signed on site in due course.

 

What effect could the works have on me?

We take care to make sure that work is completed with the minimum of disturbance to the local community but as with any major works, some traffic delays may occur. 

Although we will do our best to ensure that noise pollution is kept to a minimum, it is likely that construction noise will be heard during the working times.

How you can help us

  • Please keep children away from the works to ensure their safety.
  • Always adhere to the road closures and follow the diversion routes.
  • Please drive appropriately through the works.
  • Check your shoes before entering your property or car to make sure there is no bitumen from the works.

 

If you have any questions or queries, please visit
Enquiries: www.staffordshire.gov.uk/reportit
Website:   www.staffordshire.gov.uk/Highways/roadworks

 

 

There are no results that match your search criteria


Latest transport news
Image for Major Burton road set to be completely resurfaced

Major Burton road set to be completely resurfaced

Description
A major road in Burton will be completely resurfaced in a £600,000 highways improvement scheme that starts next week.
Date:
15 July 2024
Image for Key bridleway cleared and resurfaced for horse riders, cyclists and walkers

Key bridleway cleared and resurfaced for horse riders, cyclists and walkers

Description
A key public bridleway, situated between Aston and Madeley, has been restored and improved thanks to Staffordshire County Council's Rights of Way team.
Date:
11 July 2024
Image for Major town road scheme begins as people reminded of bus route changes

Major town road scheme begins as people reminded of bus route changes

Description
As a major road scheme begins in Stafford, bus users are being reminded of service changes put in place due to the works.
Date:
03 July 2024
Image for £1.25m Derby Road project completes in Burton

£1.25m Derby Road project completes in Burton

Description
The second phase of a major highways project to reconstruct a key route into Burton has been completed.
Date:
28 June 2024

Visit the Staffordshire Newsroom