We use strictly necessary cookies to make our site work. These cookies enable core functionality such as security, network management, and accessibility. The cookies collect information in a way that does not directly identify anyone. For more information on how these cookies work please see our privacy policy.

To agree to our use of analytical cookies, click the 'Accept cookies' button. No, give me more information.
Accept cookies Reject analytical cookies Manage cookies
 

S278 Watery Lane, Lichfield

McPhillips will be undertaking essential works in order to facilitate the entrance to a new development being carred out by Redrow Homes Limited.

Please see below the General Arrangement Plan which details the proposals and extent of works. Please also see the diversion plan and note that the nearby craft centre will be fully operational while works are taking place:

 To summarise the works will include but are not limited to the following:

  • Site clearance
  • Improvements to highway drainage and flood mitigation
  • Full depth carriageway construction
  • Provision of new and alterations to existing footpaths
  • Installation of signals under the bridge
  • New traffic signs and road markings
  • New lighting columns
  • Tree planting
  • Change in speed limit along Watery Lane
  • Provision of new and alterations to existing utilities

When are the works taking place?

The works are taking place from Wednesday 19 June 2024.

How long will the works take?

The works are expected to be take place for a period of 22 weeks.

What effect could the works have on me?

A section of Watery Lane will be closed to traffic, cyclists and pedestrians during the works. For further information see the diversion plan on this page.

We will make every effort to minimise any unnecessary disturbance and those working on site are briefed on working responsibly in the local community.

How you can help us

You can help us to get the job done with the minimum of fuss by following this advice:

  • Please keep children away from the works to ensure their safety.
  • Please drive appropriately through the works.
  • Check your shoes before entering your property or car to make sure there is no bitumen from the works.

Contact

If you have any queries regarding this work you can contact Mike Evans on the details below:

Alternatively, you can contact local County Councillors:

There are no results that match your search criteria


Latest transport news
£1.25m Derby Road project completes in Burton

£1.25m Derby Road project completes in Burton

Description
The second phase of a major highways project to reconstruct a key route into Burton has been completed.
Date:
28 June 2024
Overnight works to start in Burton next week

Overnight works to start in Burton next week

Description
A £270,000 highways scheme to improve the road outside the National Brewery Centre in Burton will start next week.
Date:
27 June 2024
Staffordshire transport gateway improvement scheme progresses with new traffic arrangements

Staffordshire transport gateway improvement scheme progresses with new traffic arrangements

Description
A scheme bringing major improvements to a key Staffordshire gateway junction is progressing well, with latest traffic management changes set to take place.
Date:
25 June 2024
Reminder that major Stafford road improvement scheme is set to begin

Reminder that major Stafford road improvement scheme is set to begin

Description
People are being reminded that a major road improvement scheme on one of the main routes into Stafford begins on July 1.
Date:
25 June 2024

Visit the Staffordshire Newsroom